Construction work at Søråni

Generator and Trafo is in place, Electric work is in progress as well.

The area at the entrance pond it is now filled and the intake-house is finished outside while the Coanda-intake are almost completed.

Two teams are now working on the pipeline and about half of the penstock is in place.