Vestre Neset in Lund
Vestre Neset power plant is located in Lund Municipality in Rogaland. The power plant utilizes a drop of 150 meters in Sætraåna, with an installed capacity of 1.5 MW from a Pelton turbine. Together with the Østre and Nedre Neset power plants, the power plant provides electricity to around 740 households. The outlet goes into the intake dam to the Nedre Neset power plant. The power plant has been in operation since 2014.
effect
income 0 NOK
volume 0 MWH
*Total production for plant
**Real time indicatiors might be delayed in some circumstances
The authorities (the Norwegian Water Resources and Energy Directorate) have set a minimum water flow in the summer and during the winter to preserve the environment and landscape.
Gross head (m) 151
Length pipeline (m) 2185
Power (MW) 1.5
Production (GWh/year) 4.3
Minimum water flow (l/s) 40
Daglig leder
Rolf Amundsen
rolf@siram.no
917 18 848
Kontaktperson i Clemens Kraft AS
Driftsdirektør
Tage Karlsen
tage.karlsen@clemenskraft.no
905 39 960