Midtun in Eivindvik
Midtun power plant is located in Eivindvik in Vestland county. The plant utilizes a drop of 111 meters and produces 2 GWh a year. The intake is a side intake from a dam that collects two rivers. The power plant utilizes one filling dam with a transfer pipe to the intake dam. The power plant has been in operation since 2013.
effect
income 0 NOK
volume 0 MWH
*Total production for plant
**Real time indicatiors might be delayed in some circumstances
The authorities (the Norwegian Water Resources and Energy Directorate) have set a minimum water flow in the summer and during the winter to preserve the environment and landscape.
Installed power (MW) 0.624
Production (GWh/year) 2
Vakttelefon
907 09 365
Stasjonsleder (new 1 st of May)
Minimum water flow throughout the year (l/s): 16
Approved for exemption from licensing.